Excavator clearing canal at ‘B’ field Sophia

D&I works already completed in the area include:- clearing of 554 rods of D/E field canal, Cummings park West Sideline- 241 rods, UG Drainage Canal- 241 rods, Dennis St Canal (North and South)- 493 rods, C Field- 187 rods, Cummings Park East Sideline and Cross Canal- 423 rods and C Field- 367 rods.
Upon the completion of works at ‘B’ field the Ministry will commence similar works at ‘A’ field, Block X, Cummings Park Middlewalk (right and left) and the cross canal from Turkeyen to Ogle.
Additional requests were also made for three 30” HDPE tubes to aid in drainage of sections of B, C and D field Sophia.