The 300 megawatts powerplant for the Gas-to-Energy project is expected to reach full capacity by June 2027, says Vice President Dr. Bharrat Jagdeo.
During his engagement with private sector stakeholders on Thursday evening at the Marriott Hotel in Georgetown, Jagdeo said the plant’s single-cycle stage was expected to come on line by the end of March 2027.
“That’s about 220 megawatts coming in. And then the combined cycle [which uses heat from the gas turbines to generate additional capacity will come in] a little bit later, June or so, for it to be completed,” the Vice President said.
Jagdeo acknowledged that the project had been significantly delayed and that costs had risen. He also addressed reports regarding a disagreement with the power plant’s contractor, Lindsayca.
That contractor had claimed that the access road to the Wales project was not ready and of poor quality. It also claimed that the site required more preparation than expected. As a result, Lindsayca wanted the government to pay it an additional US$50 million for cost overruns.
The Vice President noted that ExxonMobil handled those early works on the access road and the site on government’s behalf, adding that the government disagreed with the contractor’s claims. The matter subsequently went before the Dispute Avoidance and Adjudication Board, which issued a ruling in January 2025.
Jagdeo said the government initially intended to take the matter to arbitration but decided to negotiate with the contractor instead. He argued that arbitration would have taken years to complete, pushing the project further behind schedule.
As the nation awaits the start up of the project by the end of 2026, with full capacity expected to be reached in 2027, Jagdeo said the government will continue to subsidise the Guyana Power and Light to ensure consumers’ bills are shielded from the impact of rising fuel prices on the world market.