THE Parliamentary Committee of Supply has approved $24.7 billion in supplementary funding to advance the gas-to-energy (GTE) project at Wales in Region Three. The government has pledged to cut electricity costs by 50 per cent through the project.
Prime Minister, Brigadier (Ret’d) Mark Phillips appeared before the committee on Monday.
He explained that the funds will complete Phase 1 and secure turbines for Phase 2, among other things. All four Phase 1 turbines are expected to be running by the end of the fourth quarter of 2027.
“We want this project to continue to its end and deliver on the promise to the people,” he said. “We made a commitment to the people of Guyana that they will get 300 additional megawatts of power at 50 per cent of what they are paying for now.”
According to the PM, the revised overall cost of the project is US$956 million, up from US$759 million. He said the contractor requested an additional US$200 million, which the government agreed to pay. So far, US$130 million has been paid.
The money is needed to avoid pausing the project or going to litigation, PM Phillips emphasised. (DPI)