Works at Mahaicony Sea Defence breach must be accelerated
The work site at a breached section of sea defence.
The work site at a breached section of sea defence.

– Minister Indar
WORKS have started to repair the breach in sea defences at Content and Dantzig, Mahaicony, Region Five, but Minister within the Ministry of Public Works, Deodat Indar, who visited the site on Friday, called for those works to be accelerated.
During his visit, minister Indar met with two representatives from the two contracting firms, BK International and A&S General Contractors Inc. who were tasked with sealing the breached sections of sea defence.

The minister was informed by Ganesh Sawh, Chief Engineer, BK International that the 500-meter breach at Content should be sealed within 40 to 41 days’ time.
Minister Indar nonetheless questioned the lengthy duration of the project, which he reminded, has cost millions in losses to farmers along the embankment.
“The country has already seen the kind of damage that the flood has caused to the farmers in the area. Over 2000 farmers have lost their livelihood…what we have to do is try to get this area (or) the sea defence here fixed quickly,” the minister explained.

Minister Indar inspects a section of the sea defence works that were completed.

He added that this should have been in place since last month.
The contract for the project was awarded back in November 2019 for the rip-rap works, but the contractor complained of access to materials.
The contractor was also paid a $105 million advanced payment of the contract sum $352M although the contractor did not perform any mobilisation as yet.
Over at the Dantzig to Glaciers Lust area works were progressing. Approximately 50 per cent of the works are completed.
Meanwhile works at Prospect are nearing completion by A&S General Contractors Inc. The company was awarded approximately 1.6km of sea defence works back in November and so far, 1.25km is completed.

Minister Indar stressed the need for the existing breach of 800 meters to be sealed immediately as the violent tides can result in more damage and expenditure.
Accompanying the minister on the site visit were Chairman of Region Five, Mr. Vickchand Ramphal; Regional Vice-Chairman, Region Five, Mr. Rion Peters; Party Representative, Mr. Faizal Jaffarally and engineers from the Ministry of Public Works.

The Regional Chairman, Mr. Vickchand Ramphal said, “I am very happy that Minister Indar came to visit the work site here in the Dantzig area…this situation started approximately two years ago and very little was done to bring relief to the farmers and the citizens of this part of the region…”

Meanwhile, the Regional Vice-Chairman added, “We are looking forward to this breach being sealed as urgent as possible so that our people can go back to their normal means of earning and their normal livelihood which was disrupted as a result of this breach many years ago.”

Party Representative, Mr. Faizal Jaffarally, also shared, “I want to thank the Honourable Minister (for responding) very promptly to be here in this community this morning. I must say I am disappointed in the pace in which this work is going. This work was awarded since November last year and we expect because of how it affects the residents in this community and the contractor should have made some more effort to ensure this thing is completed.”

SHARE THIS ARTICLE :
Facebook
Twitter
WhatsApp

Leave a Comment

Your email address will not be published. Required fields are marked *

All our printed editions are available online
emblem3
Subscribe to the Guyana Chronicle.
Sign up to receive news and updates.
We respect your privacy.