–ExxonMobil relates; says there was no risk to public/staff, line’s integrity being safeguarded by continuous inspection, maintenance
EXXONMOBIL Guyana has replaced 200 metres of the Gas to Energy Pipeline, following the discovery of a nitrogen leak.
The company has sent samples to laboratories in the United States while it works out what caused the fault, ExxonMobil Guyana’s President Alister Routledge told reporters during a press conference on Tuesday.
He noted that earlier in the year the company had reported finding an “anomaly” on the line.
“Earlier this year, we did discover an anomaly on the pipeline,” the company official said.
The company first inspected the affected section and fitted a clamp to protect the pipeline’s integrity.
In recent weeks, crews returned with more equipment and new pipe.
“We removed a section of the pipe, did some more inspection, replaced that section that had the anomaly, so that we’re confident it has its integrity,” he said, adding: “Our focus is ensuring this pipeline is first of all ready for operations where the gas plant is, but secondly that [it] has its long-term integrity.”
Routledge further said: “We want to make sure that for the life of the operation of Gas-to-Energy, that this pipeline has its integrity. So that’s where work has been going on, and that maintenance and inspection activity. That’s not unusual; that’s what we do on pipelines. It’s what we do with the offshore infrastructure.”
Notably, he stressed that there was no risk to the public or staff, noting that the level of exposure was low.
Further investigations, he said, will determine the cause of the anomaly.
Guyana is anticipating cheaper electricity as the government targets December for the startup of its first gas turbine at Wales, in Region Three.
On Monday, the Parliamentary Committee of Supply approved $24.7 billion in supplementary funding to continue work on the Gas-to-Energy project.
Prime Minister Brigadier (Ret’d) Mark Phillips appeared before the committee and explained that the funds will complete Phase One and secure turbines for Phase Two, among other things.
All four Phase One turbines are expected to be running by the end of the fourth quarter of 2027.
“We want this project to continue to its end and deliver on the promise to the people,” he said, noting: “We made a commitment to the people of Guyana that they will get 300 additional megawatts of power at 50 per cent of what they are paying for now.”