From the moment the situation developed at the Canefield Substation on Thursday, Guyana Power and Light Inc. (GPL) has been on the ground, with its management and technical teams working around the clock to address the issues and restore electricity supply to affected customers across Berbice.

The team is headed by GPL’s Deputy Chief Executive Officer of Strategic Operations, Mr Bharat Harjohn, and Divisional Director of Transmission and Distribution, Ms Shaun Hamlet, with technical assistance from Kalpataru Projects International Limited.
Since Thursday evening, GPL’s technical teams have been conducting extensive troubleshooting, inspecting the wiring, electrical panels, busbar and distribution feeders. Several faulty components have been identified and replaced as part of the corrective works.
Following continued testing and assessment, technical teams have now narrowed down the fault to the grounding transformer panel. Works are ongoing.