GPL advances new 69KV transmission line on East Coast of Demerara
Director Ryan Ross, along with representatives from Guyana Power and Light Inc. (GPL) and contractor PowerChina International, recently inspected ongoing works for the erection of a new 69kV transmission line between Goedverwagting and Good Hope, East Coast Demerara
Director Ryan Ross, along with representatives from Guyana Power and Light Inc. (GPL) and contractor PowerChina International, recently inspected ongoing works for the erection of a new 69kV transmission line between Goedverwagting and Good Hope, East Coast Demerara

 

APPROXIMATELY 85 per cent of the monopole structures have been erected for the new 69KV transmission line between Goedverwagting and Good Hope, East Coast Demerara.

Recently, Director Ryan Ross, along with representatives from Guyana Power and Light Inc. (GPL) and contractor PowerChina International, inspected the ongoing works to assess the project’s progress.

Approximately 85 per cent of the monopole structures have been erected, marking significant progress on this important infrastructure project.

Once completed, the new transmission line will strengthen the national grid by improving the transfer of electricity across the network, increasing operational flexibility, supporting growing demand, and enhancing the reliability and resilience of electricity service.

The project will also provide GPL with greater flexibility to manage power flows during maintenance and network disturbances while supporting continued residential, commercial, and industrial development along the East Coast Demerara. It will replace the lines that run along the Railway Embankment.

GPL remains committed to expanding and modernising Guyana’s electricity infrastructure to support the country’s continued growth. (DPI)

 

SHARE THIS ARTICLE :
Facebook
Twitter
WhatsApp
All our printed editions are available online
emblem3
Subscribe to the Guyana Chronicle.
Sign up to receive news and updates.
We respect your privacy.