THE May/June rains have prompted the Region 6 (East Berbice/Corentyne) Regional Democratic Council (RDC) to work in collaboration with the New Amsterdam Mayor and Town Council (M&TC) to ensure that all drainage facilities within the municipality are cleared and prevent extensive flooding.
Speaking to the Guyana Chronicle on Tuesday, the Regional Drainage Supervisor, Mr. Sewdat Singh said the works were proceeding smoothly until the M&TC sluice attendant became irate for no given reason and withdrew his support when the drainage and irrigation (D&I) workers were about to clear the Winkel/Tucber canal.
According to Singh, his responsibility lies in maintaining interlock and main drains within the township but, based on a request by the Regional Chairman, Mr. Permaul Armogan, he decided to lend support to the municipality since its drainage supervisor is on official leave.
Singh said they were working well on Smythfield Canal up to the point of clearing the Winkel/Tucber waterway and the attendant was asked to open the sluice so as to allow fresh water to flow in, then run out later avoiding the workmen having to put up with smelly, stagnant drift.
But the latter was annoyed, verbally abused the workers and refused to hand over the winch that is used to raise the sluice door, resulting in a snag.
Singh said, at that stage, the sluice attendant declared that he was not taking instructions from anyone attached to the RDC as he is an M&TC employee.
The drainage supervisor said he had to divert the workers to clear the Angoy’s Avenue/Vryman’s Erven canal which was scheduled to be done during another phase of the project and a complaint was lodged with the Acting New Amsterdam Town Clerk, Mrs. Sharon Alexander.
Singh said he highlighted the importance of having the Winkel/Tucber Canal cleared as soon as possible.
He also pointed out that his workforce declined from 50 workers to just under 25 workers, making it extremely strenuous for them to be abused while working in such conditions.
For several years, residents of the eastern section of New Amsterdam experienced severe floods since the area happens to be the lowest part of the township. However, with the implementation of the D&I Project, some five years ago, the situation was relieved unless there is incessant rainfall and high tides which contribute to a slow draining process.