Hope Canal project nearing completion – Dr. Ramsammy
Works ongoing in mid-January at the Northern Relief Channel at the Hope Canal, East Coast Demerara
Works ongoing in mid-January at the Northern Relief Channel at the Hope Canal, East Coast Demerara

THE East Demerara Water Conservancy (EDWC) Northern Relief Channel, Hope Canal, is “presently completed,” according to Agriculture Minister, Dr. Leslie Ramsammy.“Presently the project is completed, for the large part,” he confirmed, in an invited comment.

The project’s four components include: the more than 10-kilometre channel; the head regulator; the eight-door sluice; and the EDWC Northern Relief Channel Public Road Bridge. The latter was completed and commissioned last February.
The Agriculture Minister acknowledged, however, that there are “minor works” that can only be completed once the structure is at a particular operational level.
Dr. Ramsammy said, “The Head Regulator is completed, but we are presently waiting to connect the channel with the EDWC. This will be done when the whole channel is ready for operation.
“In the meantime, we continue to test the operation of the doors, ensuring that the lifting mechanisms are working smoothly, that the seals on the concrete joints are effective and we are ensuring that remedial works to the Eastern Door for smooth lifting are completed.”
The more than 10-kilometre channel, he added, is 98 per cent completed, given that some 500 meters of residential passes, on the West Dam end of the Hope Canal, have been left untouched.
“Earthen works to ensure continuous flow of the channel at the Crown Dam, Mango Tree Dam, Dam at Hope Site Office, Railway Embankment and High Level Sluice have to be completed. These are minor works and will take less than a week to complete. However, for the convenience of residents, we have left these areas incomplete,” the Agriculture Minister said.
“The only outstanding works remaining, as it relates to the heavy level outfall sluice, is on the Control Building, which is presently under construction. Electrical works will follow the completion of the building, installation of lifting mechanisms (components procured and presently in Guyana) and scour protection (source from Gabion Baskets and Gabion Stones). These works should not last more than two weeks,” Dr. Ramsammy assured.
Additionally, the actual testing of the functionality of the channel will have to await the availability of an adequate volume of water to fill the channel.
The contractor for the project is Courtney Benn Contracting Services.
Construction on the project began in February 2011, with an estimated 18 months for completion, and the deadline for the project was initially set for June 2013, but was subsequently extended to the end of August, and then once again extended to December 31, 2013, then to June 30, 2014.
UNFORSEEN CHALLENGES
The EDWC Northern Relief Channel, the Hope Canal, which missed its June 30 deadline for completion, was given a new deadline in the latter part of July, when its completion was raised at the Parliamentary Sectoral Committee on Natural Resources and the Environment. The Agriculture Minister, when he appeared before the Committee, disclosed that the project will be completed in seven weeks, by September. However, this deadline has also passed due to unforeseen challenges.
LIQUIDATED DAMAGES
The Minister, in a prior comment, stated that given the continued delays with the project, the issue of liquidated damages is not off the table. “The accommodation of the contractor does not mean that the contractor will escape liquidated damages,” he said.
The Agriculture Minister stressed too the quality of work produced by the contractor has been quality work. “Some of the difficulties that the contractor has encountered can be resolved by the ministry, and so all we are doing is working in partnership with the contractor so that those difficulties are removed,” he said.
ANSWER TO FLOODING IN MMA
Indications were that the US$15M Hope Canal project, which is expected to be the answer to the flooding experienced in the Mahaica/Mahaicony/Abary (MMA) areas during rainy periods, would be operational as the rainy season sets in. Residents in the MMA area over the years have lost crops and cattle in floods, during the rainy period. As seen in the past, when the Maduni sluice has to be opened to drain the East Demerara Water Conservancy, residents in the MMA area have to battle a rise in the Mahaica Creek – making the completion of the Hope Canal something that is much needed.
The East Demerara Water Conservancy in the past had 10 discharge points, with three on the East Bank of Demerara discharging into the Demerara River; two at Mahaica; and five discharge points on the East Coast of Demerara – all leading to the Atlantic Ocean. Their closure made the Hope Canal an even greater necessity, in order to facilitate increased and direct discharges into the Atlantic.

 

SHARE THIS ARTICLE :
Facebook
Twitter
WhatsApp
All our printed editions are available online
emblem3
Subscribe to the Guyana Chronicle.
Sign up to receive news and updates.
We respect your privacy.