THE Ministry of Public Works has dismissed as misleading a report suggesting that the cost of the Government Office Complex has climbed to $19.6 billion, maintaining that the project remains within its approved contractual budget as presented to Parliament.
In a statement issued Monday, the Ministry of Public Works responded to a February 16 article published by Kaieteur News, asserting that the figure cited does not accurately reflect information disclosed in the National Assembly of Guyana.
According to the ministry, the total contract sum for the Government Office Complex stands at $15,874,143,298, which represents the full approved cost for execution of the project’s defined scope of works. Officials stressed that no increase to $19.6 billion has been established.
Financial data presented during the 2026 budget process show that $8.67 billion, or just over 53 per cent of the contract value, was expended during 2025, leaving a balance of approximately $7.19 billion to complete the project.
The ministry said these expenditures reflect significant construction progress, including the completion of piling and foundation works, major advancement of structural components now estimated at 78 per cent completion, as well as site preparation and early procurement of long-lead materials aimed at reducing risks associated with global supply chain disruptions.
Officials further clarified that confusion arose from references to a broader budget line titled “Government Buildings,” which encompasses multiple programmes nationwide rather than the single office complex project. That allocation includes rehabilitation and expansion of existing state facilities, ongoing maintenance and management of government properties, and consultancy and operational services under the ministry’s wider portfolio.
“Attributing the entire allocation under ‘Government Buildings’ solely to the Government Office Complex is factually incorrect and creates unnecessary public confusion,” the statement noted.
Looking ahead, the project is expected to transition fully into advanced structural works, followed by installation of mechanical, electrical and plumbing systems, façade construction and interior finishing. The ministry projects overall progress to increase from about 49 per cent at the start of 2026 to roughly 85 per cent completion by the end of the year.
Reaffirming its commitment to transparency, the ministry said financial and execution updates provided to Parliament clearly demonstrate that the development remains within its approved contractual and budgetary framework.
The Government Office Complex forms part of broader efforts to modernise public infrastructure and centralise government services, with officials maintaining that the project continues to advance according to plan.