THE Ministry of Public Works (MPW) has joined forces with the Lethem Mayor and Town Council (M&TC) and the Regional Democratic Council (RDC) of Region Nine to address the pressing issues at the Pirara Bridge, a critical juncture on the Linden-Lethem corridor.
In a collaborative effort, officials convened to devise a strategic plan aimed at alleviating the challenges faced by commuters traversing this vital transportation route.
The recent joint meeting involving representatives from the MPW, Lethem M&TC, and RDC 9 culminated in the formulation of a comprehensive four-point action plan. Here are the key highlights of the proposed initiatives:
1. TEMPORARY TIMBER DECK:
To facilitate smoother passage for light to medium-weight vehicles, half of the new bridge’s completed piers and abutments will be equipped with a temporary timber deck.
The contractor is currently procuring suitable timber and anticipates commencement of installation within the week.
2. PHASED CONSTRUCTION:
Upon completion of the temporary deck, construction activities will transition to the second half of the bridge using steel beams and a concrete deck.
Traffic management measures will be implemented to ensure a seamless shift of vehicles to the finished section, facilitating uninterrupted work on the remaining half.
3. TEMPORARY BOAT ASSISTANCE:
In the interim period before the wooden deck becomes operational, the Lethem M&TC, in collaboration with the RDC, will extend temporary assistance to travellers crossing the affected area by boat.
4. REPAIRS ON OTHER AFFECTED SECTIONS:
Concurrent efforts are underway to address additional sections of the road that have been adversely impacted by flooding.
Motorists are advised to exercise caution, particularly in areas prone to high water levels.
Emphasising their dedication to the well-being and safety of commuters, both the MPW and local authorities reaffirm their commitment to exploring every viable avenue to ensure the swift and secure passage of individuals through the corridor. As collaborative efforts intensify, stakeholders remain resolute in their resolve to surmount the challenges posed by the Pirara Bridge situation, underscoring the significance of a cohesive and coordinated approach in addressing critical infrastructure issues.