cites encumbrances and challenges
THE National Drainage and Irrigation Authority (NDIA), under the Ministry of Agriculture, has issued a response to criticism from Opposition Member of Parliament, Ganesh Mahipaul, regarding several pump station projects. In a statement addressing Mahipaul’s concerns, NDIA highlighted key reasons for delays in these projects.
Mahipaul’s recent call for answers from the NDIA focused on incomplete pump station projects, including those at Charity, Cozier, A-Line, Canal No.1 Sluice, Cottage, and Black Bush Polder Frontlands.
NDIA clarified that these pump station projects are managed by experienced consultants who have supervised successful projects in the past. The project engineers at NDIA also possess significant experience in constructing pump stations. All projects received extensions from the National Procurement and Tender Administration Board (NPTAB), justifying the delays.
CHALLENGES AND DELAYS:
Charity Pump Station (Region No.2): Squatters occupied the site, leading to several months of negotiations and police involvement. However, work is progressing, and pumping equipment is expected soon.
A-Line Pump Station (Region No.3): Encumbrances, including shops, storage huts, and utilities, had to be removed, resulting in several months of consultations and compensation efforts before relocation.
Canal No.1 Pump Station (Region No.3): Delays occurred due to the need for approval to demolish a community centre building within the construction zone. Engagements were made for relocation, and foundation piles are now being driven.
Cottage Pump Station (Region No.5): Erosion of the main access dam necessitated the construction of a bridge and access dam, causing significant project delays.
Black Bush Polder Frontlands Pump Station (Region No.6): This project was terminated on September 25, 2023, due to poor quality of performance. It will be re-tendered soon.
NDIA expressed disappointment that Mahipaul did not seek information from the organisation before resorting to the media. The authority viewed Mahipaul’s allegations as misconceived and misleading, particularly statements about mismanagement and inefficiency.
NDIA emphasised that extensions were lawfully granted for the projects, and work is currently underway on all except one. It also mentioned inherited challenges from the previous administration, such as the procurement of “fire pumps” as drainage pumps, which remain inoperable, costing the treasury significant amounts.
While welcoming objective scrutiny and constructive criticism, NDIA asserted its commitment to working transparently, accountably, efficiently, and competently with all stakeholders.