Resurfacing of Linden/Lethem road to be completed shortly

The resurfacing of critical sections of the Linden/Lethem road project, which has reduced the travel time from 13 plus hours to seven, will be completed in another seven days. The sections were compacted with lateritic material. lethem1
The multimillion dollar project, which commenced in September 2014, was executed in phases by Troy Resources; Omai Gold Mines (OGM); Demerara Timbers Limited (DTL); Mekdeci Machinery and Construction (MMC) and Vevakanand Dalip Enterprise (DALIP).
Two hundred and seventy-six miles of road was upgraded under the project.
Additionally, in an effort to improve visibility along the busy thoroughfare, extensive bush cutting was done especially in the vicinity of the Iwokrama Concession.
Below is a breakdown of the travel time:

From To Distance/miles Previous Travel Time/hr Current Travel Time/Hr
RockStone Junction Omai Turn Off 65 3.5 1.5
Omai Turn Off Frenchman Junction 19 0.75 0.75
Frenchman Junction Kurupukari 51 3.5 1.25
Kurupari Annai 65 3 1.5
Annai Lethem 76 3 2
Total 276 13.75 7

The Ministry is advising drivers to reduce their speed on the roadway to curtail the risk of accidents.

SHARE THIS ARTICLE :
Facebook
Twitter
WhatsApp
All our printed editions are available online
emblem3
Subscribe to the Guyana Chronicle.
Sign up to receive news and updates.
We respect your privacy.