…following Cabinet’s voicing concern on delays
TECHNICAL advisor to the Minister of Transport and Hydraulics, Walter Willis, says President of Synergy Holdings Inc, Makeshwar ‘Fip’ Motilall, is in the process of speaking with a pair of potential sub-contractors with a view to speeding up works on the Amaila Falls road, following Cabinet’s strong suggestion in this direction.
Speaking to this newspaper yesterday, Willis said, “We advised him that he should sub-contract. He started discussions with a pile-driving entity and a transport entity to haul materials.” Motilall’s company Synergy Holdings Inc secured a US$15M contract for the construction of the road leading to the site of the Amaila Falls Hydroelectric Project. The progress of the works, however, has been dogged by rain earlier in the year and a shortage of materials and manpower, prompting Cabinet to consider the option of Synergy’s sub-contracting elements of the ongoing works.
According to Willis, the pile driving entity will be expected to drive some 300 plus piles in preparation for the construction of a bridge.
“We are meeting with him tomorrow and Saturday,” said Willis. “Things have picked up in the last three weeks. The design for the superstructure of the Kuribrong bridge has started and Motilall has entered into discussions with the supplier of the pontoons for other bridges,” Willis said, adding that work is ongoing in sections 6 and 7 of the road.
Willis believes that if the two entities are sub-contracted and the work picks up further, then the August timeline for the opening of the road for light, four-wheeled drive vehicles seems possible.
Willis however noted that government at this point could only advise Motilall, whom he said was receptive to the idea. Willis said if government were to appoint an entity to complete the works, it would have no legal recourse for claiming lateness penalties as stipulated in the contract should the work still not be completed within the specified time-frame.
When asked whether the Government must have a say in determining whether the contractors are suitable for the magnitude of the works to be undertaken, Willis said that when Synergy officially submits the names of the entities to the Ministry of Works, the ministry will at that point give either a no-objection or an objection.
Rafael Herz, Senior Vice President of Sithe Global Group, the developer of the hydro, told a media conference on March 22 that the road is a critical part of the project and having it completed on time and to the specifications required is very important.
“Sithe’s interest and collaboration with the government with respect to the road is to help as much as we can to ensure that the road does continue its path of construction with the time-line requirements, and with the specifications that are needed. We are confident that this will be achieved,” he had said.