FOLLOWING Guyana Goldfields Inc last week, another Canadian mining company, Goldsource Mines Inc this week reported satisfactory progress in construction of its own gold mine located at Eagle Mountain in Region 8 (Potaro/Siparuni), disclosing that it is targeting the commissioning of a 1,000 tonnes per day open pit gravity plant by year end.Goldsource Mines said that construction is proceeding on schedule and on budget for the recovery of an estimated 980,000 ounces of gold (188,000 ounces indicated and 792,000 inferred ) with strong potential for expansion.
The plant has estimated pre-production capital costs of US$5.9 million but post-commissioning cash operating costs of under US$500 per ounce of gold.
Yannis Tsitos, President and Director stated, “We are pleased with Eagle Mountain’s construction progress with the first shipment of processing plant equipment on budget and schedule in June. This new equipment will include two SB2500 Falcon concentrators, gold recovery room, refinery, pumps, electrics and on-site laboratory. We have assembled a strong team of experienced professionals to manage the construction of Eagle Mountain and fully expect to deliver Phase I on-time and budget.”
Tsitos said further that several significant construction activities are currently on-going at Eagle Mountain.
The detailed engineering of a Sepro gold processing plant has been completed while delivery of the first package for the gold processing plant from Sepro Minerals Systems from Canada and the United Kingdom is 95% complete.
Delivery of Package No.2, another section of the said processing plant from Canada and Mexico is 20% completed.
10K ROAD, EIGHT NEW BRIDGES
Rehabilitation of the existing 10-kilometre road between Mahdia town and Eagle Mountain camp including construction of eight new bridges is 75% completed while procurement and purchase of mining equipment, including the most recent acquisition of a new excavator and loader, is 50% completed.
Other works in varying stages of completion include pre-production auger drilling program for confirmation and condemnation (75% completed); recruitment of key operations personnel (15% completed).; camp facility rehabilitation and upgrades (15% completed); site preparation of plant and initial mining area (10% completed) and procurement and purchase of secondary gold processing plant for exploiting existing old tailings area (10% completed).
The Eagle Mountain project, located close to Mahdia is a joint venture between Goldsource Mines and local company Kilroy Mining Inc.
The two companies decided to collaborate in August last year since under Guyana’s laws a medium scale mining permit can only be held by a Guyanese national.